two houses

Where an adjoining owner’s express consent is required for scaffold, hoarding or crane access such consent will generally be subject to conditions and one of the more contentious conditions is the payment of a consideration.

This will generally be in the form of a weekly payment for a fixed period with a more punitive sum payable in respect of any over-run.

An adjoining owner can request any amount they wish but their negotiating strength will depend upon what alternative options are available to the building owner. A good example would be a situation where a developer could complete the works with the use of either a standard tower crane or a crane with a considerably more expensive luffing jib which was capable of working within a tighter radius and thus removing the need for access.

In such circumstances the quantum of any payment might be based on the additional cost associated with the alternative option.

If there are no alternatives available the quantum of any consideration should be at least loosely based on the circumstances rather than plucked out of the air by the adjoining owners. The payment should reflect:

  1. The inconvenience suffered by the adjoining owner e.g. by the loss of a portion of their land. If the land that is put out of use is a drive way the inconvenience suffered would be much greater than losing a narrow strip at the end of the garden.
  2. Reduced living conditions due to loss of light. This would obviously be more significant if it is the light to a living room or kitchen that is injured as opposed to, say, a bathroom.
  3. Disturbance from noise, vibration or dust associated with the works. The conditions within the Licence should endeavour to alleviate these issues.

None of these are generally easy to quantify but an experienced surveyor should have a frame of reference upon which to base advice.

Where a developer erects a crane and oversails an adjoining owner’s land without agreement the adjoining owner has 2 remedies available to them; an injunction or the payment of a Licence fee through court proceedings (compensation). However, if they peruse the latter option they cannot hold the contractor to ransom by demanding an unreasonably high sum.

In Woolerton & Wilson v Richard Costain Ltd [1970] an adjoining owner entered negotiations with the contractor but refused the contractor’s offer of £250 per week plus a promise to insure against any damage that might be caused. When the contractor erected the crane the adjoining owner applied to court for an injunction.  The court granted the injunction but suspended it for 2 years (which would take it beyod the required period of access). Courts will therefore consider at a wide range of issues including whether or not the contractor has acted reasonably in offering payment for a licence fee.

It is occasionally in the adjoining owner’s interest to agree reciprocal rights as an alternative to a cash consideration. If an adjoining owner is likely to require access for their own works in the future this would be a way of ensuring that they get it. Any such agreement would need to be registered against both titles at the Land Registry and be binding upon successors in title.

Contact Us

If you require any advice on matters relating to access please do not hesitate to contact us

I was put at ease by the professional way In which this survey was conducted I highly recommend Peter Barry All aspects were considered my home Was examined for any potential problems That may be caused by the works being Carried out by the neighbouring property . Photos were skilfully recorded and a Drone was used to take pictures of the roof . Peter Barry Surveyor truly did a fantastic Job acting in a professional manner at all Times . And showing respect for my home And security and I can only prise them , Many Thanks Rachel
I was a neighbour of someone who wanted to do some changes to their dormer into a full loft conversion. The surveyor sent to review our shared walls was very young professional and helped answer all my questions and concerns. The emails from the firm were very formal, else and they were very reachable by telephone. I didn’t pay as my neighbour was carrying out the works so I can’t comment there. I would consider using this firm for further works personally
Very responsive and proactive. Would highly recommend
Great surveyor. Professional and very good service for our party wall matter. Thank you.
The service provided was party wall and was professional especially it got done swiftly and in good time and did not delay the building work of the next door neighbor. N13, Eaton Park Road
All good thankyou!
Call Now Button