When is an Interim Injunction Justified to Stop Work to a Party Wall?

Thursday, 15th July 2010
Party Walls | Surveying

It’s always difficult to advise people who call us up when a neighbour has started work which comes within the scope of the Party Wall Act but have not served the required notice.

It is one of the shortcomings of the Act that there aren’t any penalties for non-compliance. The only remedy available to a Building Owner is to apply for an interim injunction to stop the work while the merits of their claim are considered. To those unfamiliar with the courts that can seem to be a big step.

A case from 2007, Udal v. Dutton, provided some direction on the criteria that must be met to justify an interim injunction. In that case a Building Owner had commenced the demolition of a party fence wall dividing the rear gardens of 2 houses in Wandsworth SW11 before an award had been agreed by the party wall surveyors and served on the owners.

The criteria set out by the court were:

  1. That there must be a serious issue to be tried
  2. That the balance of convenience must favour the grant of an injunction
  3. That it must be shown that damages would not be an adequate remedy

Undertaking work to a party wall without serving notice constitutes a trespass so most courts would consider that to be a serious issue. If the Adjoining Owner is undertaking Section 6 (excavation) works the argument would be that support has been removed and there is a significant risk of movement.

In Udal v. Dutton the court decided that the balance of convenience favoured an injunction so that what was left of the wall could be preserved and what had been removed replaced with a temporary barrier. If the proposed work involved inserting a couple of beams into a party wall (typical of a loft conversion) it would be more difficult to argue for an injunction as the notifiable work would likely be completed before the application went before a judge.

The court’s view in Udal v. Dutton was that homeowners are generally more concerned with preserving their homes than recovering damages and therefore considered damages to be an inadequate remedy.

It should be noted that it is not always necessary to prove that an interim injunction is necessary for it to be granted. In most cases the court will require an applicant to give a cross-undertaking in damages prior to granting the injunction. In effect, the undertaking means that the applicant will be required to pay damages to the defendant arising from the grant of the interim injunction if it transpires that the injunction was not justified.

You should always seek legal advice before applying for an interim injunction. You can read a summary of the Udal v. Dutton case.

We recently used Peter Barry Chartered Surveyors to handle our party wall agreement and were extremely pleased with the service we received.

From start to finish, the team was professional, knowledgeable, and very responsive. They explained the party wall process clearly, kept everything moving efficiently.

Communication was excellent throughout, and we felt confident that everything was being handled properly and fairly for all parties involved.

I would highly recommend Peter Barry Chartered Surveyors to anyone needing party wall advice or surveying services.
Professional, diligent and very quick. I was offered a call with David Breeze after his survey, which was incredibly helpful - as he was able to explain "in real English" what was in the report and which elements I needed to be most/less concerned about. Would highly recommend!
Very pleased so far with Katie's thoroughness and support
Long may it continue!
We used Peter Barry Surveyors for a Schedule of Condition Report. The service was provided at short notice which we were extremely grateful for. Following our initial contact with Tracey Stephens who was really helpful to us, we had a visit from Argash Thasan arranged within a few days of our first contact. Argash provided us with a great service. He was polite, friendly, and professional, answered our questions clearly, and with knowledge and expertise of party wall matters. We received a thorough report and a detailed range of accompanying photos. We would highly recommend the services of Peter Barry Surveyors.
Peter Barry has been very professional throughout the process of conducting a level 3 building survey and feasibility report. The report itself was very detailed with plenty of images to support the text. We also had opportunity before and after to speak to the surveyor at length which was very helpful.
Peter Barry Chartered Surveyors were great to deal with. Clear communication throughout, the inspection was arranged quickly, and the Level 3 report was thorough and easy to follow. The admin team were also very helpful and kept everything moving smoothly. Would happily recommend.
Call Now Button