LATEST BLOG POSTS: Party Walls

Welcome to Peter Barry’s blog posts. You’ll find a range of topics focussing on issues that are important to our clients where we try to answer the questions that we regularly get asked.

Party Wall Questions #10

Saturday, 3rd September 2011 | by: Peter Barry

Question A Building Owner’s basement conversion works damage the party wall to such an extent that the remedy is partial re-building. The Adjoining Owner elects to receive a payment in lieu of the repair as they don’t trust the Building Owner’s contractor to undertake the works. Prior to carrying out the repair does the Adjoining Owner (now Building Owner) need to serve notice on the ...

Question A Building Owner’s basement conversion works damage the party wall to such an extent that the remedy is partial ...

Read more >>

Party Wall Questions #9

Wednesday, 31st August 2011 | by: Peter Barry

Question If a Building Owner appoints a surveyor on behalf of an Adjoining Owner in accordance with Section 10(4) can that ...

Read more >>

Party Wall Questions #8

Thursday, 25th August 2011 | by: Peter Barry

Question An Adjoining Owner is served with a notice just days before they are due to exchange contracts on the sale of ...

Read more >>

Party Wall Questions #7

Wednesday, 17th August 2011 | by: Peter Barry

Question The Government Explanatory Booklet lists certain jobs as being so minor they do not warrant the serving of a ...

Read more >>

Party Wall Questions #6

Thursday, 17th March 2011 | by: Peter Barry

Question A leasehold owner of a ground floor flat proposes to underpin the rear external walls (not party walls) of their ...

Read more >>

Party Wall Questions #5

Tuesday, 15th March 2011 | by: Peter Barry

Question What factors should a Surveyor consider when setting the hourly rate to use when calculating expenses for ...

Read more >>

Party Wall Questions #4

Saturday, 12th March 2011 | by: Peter Barry

Question I recently arranged to meet a Building Owner’s surveyor on site to prepare a schedule of condition only to find that the foundations to the proposed rear extension had already been excavated and cast. In light of recent case law were we within our rights to produce an Award authorising the excavation work retrospectively. No damage had been caused at the time of our inspection ...

Question I recently arranged to meet a Building Owner’s surveyor on site to prepare a schedule of condition only to find ...

Read more >>

Party Wall Questions #3

Tuesday, 1st February 2011 | by: Peter Barry

Question Can a Building Owner cast a new mass concrete foundation above and alongside the projecting concrete foundation to ...

Read more >>

Party Wall Questions #2

Wednesday, 26th January 2011 | by: Peter Barry

Question An Owner of a terraced house wishes to convert his original first floor balcony to an additional room. The balcony ...

Read more >>

Party Wall Questions #1

Saturday, 22nd January 2011 | by: Peter Barry

Question An Owner plans to add an additional floor to the back addition of his late Victorian terraced house by raising a ...

Read more >>
Clear, speedy communication and good service.
Highly professional, efficient and courteous service, giving a detailed explanation of criteria for calculating the premium for a lease extension.
From the first moment of contact, this business has achieved everything it was contracted to do, efficiently and professionally. I'm only too happy to recommend them.
Professional service; responsive customer service; quick set up and delivery times; provided useful feedback on the report.
They were very quick and efficient at getting me a valuation on my flat for doing a section 42 lease extension and the communication was very clear.
Call Now Button