Glossary of Party Wall Terms

Friday, 16th March 2012
Party Walls

Some of the terminology around The Party Wall etc. Act 1996 is confusing to the layperson so we thought it would be a good idea to draw them all together in this glossary. If there is anything that you think is missing drop us a line and we’ll update.

The ‘Act’The Party Wall etc. Act 1996.
Owner

 

Defined by the Act as anyone having an interest in a property of greater than 1 year i.e. not an Assured Shorthold tenant
Building Owner

 

An Owner proposing to carry out works that fall within the scope of the Act.
Adjoining  OwnerAn Owner of any neighbouring property to whom the proposed works are notifiable.
OccupierA person that resides at an Adjoining Owner’s property; other than the Adjoining Owner themselves. Occupiers do not have to be notified but do have other rights under the Act.
Notifiable WorksAny works proposed by a Building Owner that fall under sections 1, 2 or 6 of the Act.
Party Wall NoticeA formal document that is served on an Adjoining Owner by a Building Owner, providing details of the proposed work and when it is expected to commence. An Adjoining Owner can either consent or dissent to a notice.
ConsentTo agree to the proposed works.
Dissent

 

The opposite of consent – if an Adjoining Owner dissents they create a dispute under the Act.
DisputeThe term used in the Act when an Adjoining Owner does not consent to the works upon receipt of a notice. The Owners are deemed to be in dispute if consent is not given with 14 days of the notice being served.
AwardOwners that are ‘in dispute’ must appoint surveyors (or agree to appoint a single surveyor). The surveyors resolve the dispute by agreeing the terms of an Award and serving it on the Owners.
Party Wall AgreementSee ‘Award’
Counter NoticeUpon being served a notice by the Building Owner, an Adjoining Owner can serve a counter notice, requesting him to carry out specific works.
Line of JunctionAn imaginary line dividing the lands of adjoining owners. Unlike a boundary line the Line of Junction also extends upwards.
Section 1 of the ActCovers construction of new walls on the line of junction between two Owners. Building astride the line of junction is only possible with the Adjoining Owner’s written consent. Notice should be served one month before the proposed start date of any section 1 works.
Party StructureA wall, floor or partition separating adjoining properties.
Section 2 of the ActCovers works to an existing Party Structure. There are a wide scope of works that fall under this category, including raising, repairing, demolishing and rebuilding, cutting into, cutting away projections and exposing a party wall. Notice should be served two months before the proposed start date of any section 2 works.
Adjacent ExcavationDigging close to an Adjoining Owner’s property – covered by Section 6 of the Act. Notice served under Section 6 of the Act is often referred to as a ‘Notice of Adjacent Excavation’.
Section 6 of the Act

 

Covers adjacent excavations within 3 and/or 6 metres of an Adjoining Owner’s property. If excavations are within 3 metres of an Adjoining Owner’s building and deeper than the base of their foundations, they will be notifiable under this section. The 6 metre rule will normally only be applicable if the work includes piled foundations. Notice should be served one month before the proposed start date of any section 6 works.
3 Metre & 6 Metre NoticesAlternative names for a Notice of Adjacent Excavation depending upon the relevant distant.
Party WallThere are two types recognised under the Act:

Type (a) – a wall that stands astride the boundary belonging to two or more different owners.

Type (b) – a wall that stands wholly on one owner’s land but is used by two or more owners to separate their buildings.

Party Wall SurveyorA surveyor appointed by either, or both, of the Owners. Anyone can be appointed as a Party Wall Surveyor except the Owners although an understanding of construction and procedures under the Act is desirable. Surveyors appointed under the Act have an obligation to act impartially.
Building Owner’s SurveyorA surveyor appointed by the Building Owner
Adjoining Owner’s SurveyorA surveyor appointed by the Adjoining Owner
Third SurveyorIs selected at the outset by the two appointed surveyors but is only called upon where there is a matter that they themselves cannot resolve.
Agreed SurveyorA surveyor appointed by both the Building Owner and Adjoining Owner.
Rights of EntryWhere work is authorised by the Act and access to the Adjoining Owner’s property is necessary to execute said work that right is provided by Section 8 of the Act.
Security for ExpensesSection 12 of the Act gives an Adjoining Owner the right to request Security for Expenses i.e. ask that funds are placed in an independent account by the Building Owner in case the works are started but not finished. If the Building Owner refuses such a request the matter passes to the appointed surveyors to resolve.
Working with Joanne, Joe, and our surveyor Shaun, through Peter Barry was a pleasure. We were buying a property in need of complete renovation, and they were able to customise the approach to cover only the parts of a home survey that were relevant for us, as well as advise on the likely feasibility of the renovations we had proposed. We would happily work with Peter Barry again.
Very professional and would recommend.
My wife and I engaged Peter Barry Surveyors to carry out a Level 2 RICS survey, and we were extremely satisfied with both the customer service and the professionalism with which the survey was conducted. The report we received was thorough and included several useful observations and recommendations. For instance, the surveyor identified some structural issues with the roof of the property we are considering purchasing, which we had not noticed ourselves. We were also offered a follow-up call with the surveyor to discuss the findings in more detail, which was very helpful. I would also like to give special recognition to Joanne for her outstanding support and responsiveness throughout the process. She was incredibly professional and helpful, always providing the information we needed and promptly assisting with coordinating follow-up questions with the surveyor. Overall, great service, excellent communication and a very quick turnaround time. Highly recommended!
We were extremely happy with the service we received from Peter Barry - prompt, efficient and very professional. Would definitely use them again if required.
Response from the owner:Thank you for your kind feedback. We're delighted to hear that you found our service prompt, efficient and professional. We appreciate your comments and look forward to assisting you again in the future.
Excellent experience. We used them for a specific defect report. Very helpful surveyor who talked me through everything and outlined a range of possible solutions. Highly recommend.
Response from the owner:Thank you for your kind feedback. We're delighted to hear that our surveyor took the time to talk you through the specific defect report and outline a range of possible solutions. We appreciate your recommendation.
I had a great experience with Peter Barry Chartered Surveyors and used their services for a party wall agreement. I worked with Callum, who was extremely professional, and knowledgeable throughout. Communication was excellent, and he always followed up promptly. I would highly recommend their services to anyone looking for a reliable and professional surveyor.
Response from the owner:Thank you for your kind feedback. We're delighted to hear that Callum was professional and knowledgeable throughout your party wall agreement, and that communication was excellent. We'll be sure to pass your comments on to him, and we appreciate your recommendation.
Call Now Button